Appears old movement. Moniter |
|
1 |
Crack Stitching - Provide 2 No rows of Helibar or |
|
1 |
Crack repairs |
|
2 |
Crack repairs & tying in of stair tower to main bl |
|
1 |
Crack repairs / pointing. |
|
1 |
Crack repairs / repointing |
|
1 |
Crack repairs. |
|
1 |
Extra tie rods may be required |
|
1 |
Further investigation by Structural Enginner, esti |
|
1 |
Loft floor overloaded - remove stored items fromlo |
|
1 |
Monitor / further investigation likely £2,000 repa |
|
1 |
Monitor for further movement if stable repair crac |
|
1 |
Monitor the abnormal movement to diagnose cause an |
|
1 |
Monitor to diagnose then spec repairs estimate fee |
|
1 |
Movement to front bay, monitor to diagnose cause a |
|
1 |
Property has abnormal structural cracking requires |
|
1 |
Provide/replace internal corner facings in bedroom |
|
1 |
Remove 1 tree at rear and 6m of shrubs and hedge t |
|
1 |
Repoint.crack 3m@backof house |
|
1 |
Repointing to cracks. |
|
1 |
Settlement probably complete |
|
1 |
Specialist crack repair |
|
1 |
Staimless ties |
|
1 |
Stitch brickwork - 1 m |
|
1 |
Stitch together 3m |
|
1 |
Strap or re-bond 3m |
|
1 |
There is abnoraml structural movement cracking to |
|
1 |
Till cracks gf and ff 16 linear metres. |
|
1 |
Trees causing subsidence |
|
1 |
Underpin front elevation |
|
1 |
Vernier Monitor |
|
1 |
assess in 6 months |
|
1 |
crack repair |
|
1 |
crack repairs / re-pointing |
|
1 |
examine further |
|
1 |
improve lintel end bearing |
|
1 |
monitor cracking between windows |
|
1 |
monitor for progress |
|
1 |
monitor gable crack recently re-pointed |
|
1 |
monitor small crack bricks |
|
1 |
movement of wall abutting chimney flue |
|
1 |
repair horizontal crack to back wall |
|
1 |
review underpinning already done, may have been on |
|
1 |
stitch brickwork 2 m long |
|
1 |
straps x 2 |
|
1 |
tie bars |
|
1 |
tie in extn |
|
1 |
underpin / re-build bay |
|
1 |
underpin 4 m, B,R corner |
|
1 |
underpin back addition . .BA . |
|
1 |
works budget estimate £5000 + VAT |
|